• This is a political forum that is non-biased/non-partisan and treats every person's position on topics equally. This debate forum is not aligned to any political party. In today's politics, many ideas are split between and even within all the political parties. Often we find ourselves agreeing on one platform but some topics break our mold. We are here to discuss them in a civil political debate. If this is your first visit to our political forums, be sure to check out the RULES. Registering for debate politics is necessary before posting. Register today to participate - it's free!

NSA To Build $1.5 Billion Cybersecurity Data Center

American

Trump Grump Whisperer
DP Veteran
Monthly Donator
Joined
Mar 11, 2006
Messages
96,461
Reaction score
33,781
Location
Western Virginia
Gender
Male
Political Leaning
Conservative
Link

By J. Nicholas Hoover, InformationWeek
Oct. 29, 2009
The National Security Agency, whose job it is to protect national security systems, will soon break ground on a data center in Utah that's budgeted to cost $1.5 billion.
Like this story? Get a heads-up every day on important tech developments by subscribing to InformationWeek's Newsletters. Click right here to get the news delivered directly to your in box.
The NSA is building the facility to provide intelligence and warnings related to cybersecurity threats, cybersecurity support to defense and civilian agency networks, and technical assistance to the Department of Homeland Security, according to a transcript of remarks by Glenn Gaffney, deputy director of national intelligence for collection, who is responsible for oversight of cyber intelligence activities in the Office of the Director of National Intelligence.
"Our country must continue to advance its national security efforts and that includes improvements in cybersecurity," Sen. Robert Bennett, R-Utah, said in a statement. "As we rely more and more on our communications networks for business, government and everyday use, we must be vigilant and provide agencies with the necessary resources to protect our country from a cyber attack."
The data center will be built at Camp Williams, a National Guard training center 26 miles south of Salt Lake City, which was chosen for its access to cheap power, communications infrastructure, and availability of space, Gaffney said. The complex will comprise up to 1.5 million square feet of building space on 120 to 200 acres, according to the NBC affiliate in Salt Lake City.
According to a budget document for the project, the 30-megawatt data center will be cooled by chilled water and capable of Tier 3, or near carrier-grade, reliability. The design calls for the highest LEED (Leadership in Energy and Environmental Design) standard within available resources.